[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-864380":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},864380,556,1,"单选题","基坑挖土设计标高时,宜在其上部预留（），待下一工序开始前继续挖除。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","50MM～100MM",false,{"key":16,"text":17,"correct":14},"B","100MM～150MM",{"key":19,"text":20,"correct":21},"C","150MM～300MM",true,{"key":23,"text":24,"correct":14},"D","300MM～500MM","基坑开挖时，应及时采取措施防止坑壁坍塌；基坑挖土接近基底设计标高时，宜在其上部预留150mm～300mm土层，待下一工序开始前继续挖除。",{"id":6,"name":27,"category":28,"favorite":29},"江苏省B证（项目负责人）","建筑工程",0]