[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-864362":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},864362,556,1,"单选题","脚手架工程施工时，应首先由脚手架工程（）向架子班组作业人员进行安全技术交底，并有交底书，交底后双方应签字并注明交底日期。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目负责人",false,{"key":16,"text":17,"correct":18},"B","技术负责人",true,{"key":20,"text":21,"correct":14},"C","工程部",{"key":23,"text":24,"correct":14},"D","施工班长","脚手架工程施工时，应首先由脚手架工程技术负责人向架子班组作业人员进行安全技术交底，并有交底书，交底后双方应签字并注明交底日期。",{"id":6,"name":27,"category":28,"favorite":29},"江苏省B证（项目负责人）","建筑工程",0]