[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-864188":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},864188,556,1,"单选题","土方作业阶段达到作业区目测扬尘高度小于（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1.0M",false,{"key":16,"text":17,"correct":14},"B","1.2M",{"key":19,"text":20,"correct":21},"C","1.5M",true,{"key":23,"text":24,"correct":14},"D","1.8M","土方作业阶段达到作业区目测扬尘高度小于1.5m。",{"id":6,"name":27,"category":28,"favorite":29},"江苏省B证（项目负责人）","建筑工程",0]