[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-863367":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},863367,555,2,"多选题","脚手架及其地基基础应在（ ）的阶段进行检查和验收。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","基础完工后及脚手架搭设前",true,{"key":16,"text":17,"correct":14},"B","作业层上施加荷载前",{"key":19,"text":20,"correct":14},"C","每搭设完6～8M高度后",{"key":22,"text":23,"correct":14},"D","达到设计高度后",{"key":25,"text":26,"correct":27},"E","遇有七级及以上大风与大雨后",false,"ABCD","脚手架及其地基基础应在下列阶段进行检查与验收：1）基础完工后及脚手架搭设前。2）作业层上施加荷载前。3）每搭设完6~8m高度后。4）达到设计高度后。5）遇有6级及以上强风或大雨后。6）冻结地区解冻后。7）停用超过1个月。",{"id":6,"name":31,"category":32,"favorite":33},"江苏省A证（企业负责人）","建筑工程",0]