[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-863006":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},863006,555,1,"单选题","以下不符合脚手架及地基基础检查与验收时段规定的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基础完工后及脚手架搭设前",false,{"key":16,"text":17,"correct":18},"B","作业层上施加荷载后",true,{"key":20,"text":21,"correct":14},"C","每搭设完6～8M高度后",{"key":23,"text":24,"correct":14},"D","遇有六级及以上强风或大雨后","脚手架及其地基基础应在下列阶段进行检查与验收：l）基础完工后及脚手架搭设前。2）作业层上施加荷载前。3）每搭设完6～8m高度后。4）达到设计高度后。5）遇有6级及以上强风或大雨后。6）冻结地区解冻后。7）停用超过一个月。",{"id":6,"name":27,"category":28,"favorite":29},"江苏省A证（企业负责人）","建筑工程",0]