[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-862983":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},862983,555,1,"单选题","施工现场临时用电设备在（ ）台及以上者，应编制临时用电组织设计。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":14},"B","3",{"key":19,"text":20,"correct":14},"C","4",{"key":22,"text":23,"correct":24},"D","5",true,"施工现场临时用电设备在5台及以上或设备总容量在50kw及以上者，应编制临时用电组织设计。施工现场临时用电设备在5台以下和设备总容量在50kw以下者，应制定安全用电和电气防火措施。",{"id":6,"name":27,"category":28,"favorite":29},"江苏省A证（企业负责人）","建筑工程",0]