[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-862333":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},862333,554,3,"判断题","钢支撑拆除时应避免瞬间预应力释放过大而导致支护结构局部变形、开裂，并应采用同步卸载钢支撑预应力的方法对其进行拆除。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"",{"id":6,"name":21,"category":22,"favorite":23},"B证（项目管理人员）","建筑工程",0]