[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-862167":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":27,"analysis":28},862167,554,2,"多选题","基坑工程施工的监测项目应根据（）等因素综合确定。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","基坑工程安全等级",true,{"key":16,"text":17,"correct":14},"B","环境保护等级",{"key":19,"text":20,"correct":14},"C","场地特点",{"key":22,"text":23,"correct":14},"D","基坑支护形式",{"key":25,"text":26,"correct":14},"E","施工工艺","ABCDE","",{"id":6,"name":30,"category":31,"favorite":32},"B证（项目管理人员）","建筑工程",0]