[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-862133":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},862133,554,2,"多选题","对尚未完全拆除的脚手架而临时停工、休息、隔夜或临时停工的，剩余的脚手架架体上的底笆或脚手板、防护栏杆、连墙件等，必须（）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","齐全",true,{"key":16,"text":17,"correct":14},"B","安全",{"key":19,"text":20,"correct":14},"C","牢固",{"key":22,"text":23,"correct":14},"D","有效",{"key":25,"text":26,"correct":27},"E","配置",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"B证（项目管理人员）","建筑工程",0]