[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-862125":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},862125,554,2,"多选题","项目负责人应根据施工中（），进行相应的安全控制。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","人的不安全行为",true,{"key":16,"text":17,"correct":14},"B","物的不安全状态",{"key":19,"text":20,"correct":21},"C","安全费用",false,{"key":23,"text":24,"correct":14},"D","管理缺陷",{"key":26,"text":27,"correct":14},"E","作业环境的不安全因素","ABDE","",{"id":6,"name":31,"category":32,"favorite":33},"B证（项目管理人员）","建筑工程",0]