[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-862093":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},862093,554,2,"多选题","施工单位应当根据不同施工阶段和周围环境及季节、气候的变化，在施工现场采取相应的安全施工措施。施工现场暂时停止施工的，施工单位应当做好现场保护，所需费用（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","由建设单位承担",false,{"key":16,"text":17,"correct":14},"B","由施工单位承担",{"key":19,"text":20,"correct":14},"C","由监理工程师确定承担方",{"key":22,"text":23,"correct":24},"D","由责任方承担",true,{"key":26,"text":27,"correct":24},"E","按照合同约定执行","DE","",{"id":6,"name":31,"category":32,"favorite":33},"B证（项目管理人员）","建筑工程",0]