[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-861843":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},861843,554,1,"单选题","涉及深基坑、地下暗挖工程、高大模板工程的专项施工方案，施工单位还应当（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","重新测算安全验算结果",false,{"key":16,"text":17,"correct":18},"B","组织专家进行论证、审查",true,{"key":20,"text":21,"correct":14},"C","监理工程师名单",{"key":23,"text":24,"correct":14},"D","附安全预算","",{"id":6,"name":27,"category":28,"favorite":29},"B证（项目管理人员）","建筑工程",0]