[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-861842":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},861842,554,1,"单选题","施工单位应当在施工组织设计中编制安全技术措施和施工现场临时用电方案，对基坑支护与降水工程第一些达到一定规模的危险性较大的分部分项工程编制专项施工方案，并附具（），经施工单位技术负责人、总监理工程师签字后实施，由专职安全生产管理人员进行现场监督。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","安全验算结果",true,{"key":16,"text":17,"correct":18},"B","施工人员名单",false,{"key":20,"text":21,"correct":18},"C","监理工程师名单",{"key":23,"text":24,"correct":18},"D","安全预算","",{"id":6,"name":27,"category":28,"favorite":29},"B证（项目管理人员）","建筑工程",0]