[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-861716":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},861716,554,1,"单选题","凡临时用电的设施使用超过（ ）以上（含）的，应按正式线路架设。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3个月",false,{"key":16,"text":17,"correct":18},"B","6个月",true,{"key":20,"text":21,"correct":14},"C","9个月",{"key":23,"text":24,"correct":14},"D","12个月","",{"id":6,"name":27,"category":28,"favorite":29},"B证（项目管理人员）","建筑工程",0]