[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-861207":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},861207,553,2,"多选题","下列（）达到一定规模的危险性较大的工程应当编制专项施工方案，并附具安全验算结果。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","基坑降水工程",true,{"key":16,"text":17,"correct":14},"B","土方开挖工程",{"key":19,"text":20,"correct":14},"C","脚手架工程",{"key":22,"text":23,"correct":24},"D","灌浆工程",false,{"key":26,"text":27,"correct":24},"E","混凝土浇注工程","ABC","基坑支护与降水工程、土方和石方开挖工程、模板工程、起重吊装工程、脚手架工程、拆除爆破工程、围堰工程、其他危险性较大的工程。",{"id":6,"name":31,"category":32,"favorite":33},"B证（项目负责人）","建筑工程",0]