[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-860866":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},860866,553,1,"单选题","项目部安全生产定期安全检查时间要求是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","每周一次",true,{"key":16,"text":17,"correct":18},"B","每月一次",false,{"key":20,"text":21,"correct":18},"C","每季一次",{"key":23,"text":24,"correct":18},"D","每年一次","定期安全检查要求：班组安全检查应在每班的班前、班中和班后检查一次；项目部安全检查每周一次；公司（或集团公司的分支机构）安全检查每月一次；集团公司安全检查每季一次。项目部每月要进行一次安全生产综合检查，并以检查通报的形式公布检查情况；专职安全生产管理人员每日要对施工现场安全生产情况进行巡查，并做好安全检查日志的记录。",{"id":6,"name":27,"category":28,"favorite":29},"B证（项目负责人）","建筑工程",0]