[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-860824":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},860824,553,2,"多选题","危险性较大的分部分项工程专项方案实施前，（）应当向现场管理人员和作业人员进行安全技术交底。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工单位技术负责人",false,{"key":16,"text":17,"correct":18},"B","项目技术负责人",true,{"key":20,"text":21,"correct":14},"C","项目负责人",{"key":23,"text":24,"correct":14},"D","监理人员",{"key":26,"text":27,"correct":18},"E","方案编制人员","BE","专项方案实施前，编制人员或者项目技术负责人应当向现场管理人员和作业人员进行安全技术交底。",{"id":6,"name":31,"category":32,"favorite":33},"B证（项目负责人）","建筑工程",0]