[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-860066":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":27,"analysis":28},860066,538,2,"多选题","按照《建筑法》和《建设工程安全生产管理条例》的要求，模板工程施工前应编制专项施工方案，主要包括：（）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","该现浇混凝土工程的概况；",true,{"key":16,"text":17,"correct":14},"B","拟选定的模板种类(部位、种类、面积、高度)；",{"key":19,"text":20,"correct":14},"C","模板及其支撑体系的设计计算及布料点的设置；",{"key":22,"text":23,"correct":14},"D","绘制各类模板的施工图；",{"key":25,"text":26,"correct":14},"E","模板搭设的程序、步骤及要求；","ABCDE","",{"id":6,"name":30,"category":31,"favorite":32},"A证（主要负责人）","建筑工程",0]