[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-859355":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},859355,537,2,"多选题","专项方案应当由施工单位技术部门组织本单位（ ）等部门的专业技术人员进行审核。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","技术",true,{"key":16,"text":17,"correct":18},"B","经营",false,{"key":20,"text":21,"correct":14},"C","安全",{"key":23,"text":24,"correct":14},"D","质量",{"key":26,"text":27,"correct":18},"E","物资供应","ACD","专项方案应当由施工单位技术部门组织本单位施工技术、安全、质量等部门的专业技术人员进行审核，经审核合格的，由施工技术负责人签字。",{"id":6,"name":31,"category":32,"favorite":33},"A证（企业负责人）","建筑工程",0]