[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-859094":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},859094,537,1,"单选题","临时用电工程定期检查应按（ ）进行，对安全隐患必须及时处理，并应履行复查验收手续。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分部分项工程",true,{"key":16,"text":17,"correct":18},"B","企业工程",false,{"key":20,"text":21,"correct":18},"C","单位工程",{"key":23,"text":24,"correct":18},"D","单项工程","临时用电工程定期检查应按分部分项工程进行，对安全隐患必须及时处理，并应履行复查验收手续。",{"id":6,"name":27,"category":28,"favorite":29},"A证（企业负责人）","建筑工程",0]