[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-859086":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},859086,537,1,"单选题","临时用电工程必须经（ ）验收，合格后方可投入使用。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制、审核、批准部门和使用单位共同",true,{"key":16,"text":17,"correct":18},"B","送电单位",false,{"key":20,"text":21,"correct":18},"C","监理单位",{"key":23,"text":24,"correct":18},"D","使用单位","临时用电工程必须经编制、审核、批准部门和使用单位共同验收，合格后方可投人使用。",{"id":6,"name":27,"category":28,"favorite":29},"A证（企业负责人）","建筑工程",0]