[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-859075":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},859075,537,1,"单选题","夏季施工时，日最高气温达到（ ）以上，应当停止当日室外露天作业。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","30℃",false,{"key":16,"text":17,"correct":18},"B","40℃",true,{"key":20,"text":21,"correct":14},"C","50℃",{"key":23,"text":24,"correct":14},"D","60℃","施工单位应当根据工程项目所在地气象主管部门所属气象台当日发布的预报气温，调整作业时间（因人身财产安全和公众利益需要紧急处理的除外）:1）日最高气温达到40℃以上，应当停止当日室外露天作业。2）日最高气温达到37℃以上、40℃以下时，施工单位全天安排劳动者室外露天作业时间累计不得超过6h，连续作业时间不得超过国家规定，且在气温最高时段3h内不得安排室外露天作业。3）日最高气温达到35℃以上、37℃以下时，施工单位应当采取换班轮休等方式，缩短劳动者连续作业时间，并且不得安排室外露天作业劳动者加班。",{"id":6,"name":27,"category":28,"favorite":29},"A证（企业负责人）","建筑工程",0]