[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-858504":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},858504,535,2,"多选题","业主自主管理的模式下，在设计阶段，建设单位采用BIM技术进行建设项目设计的展示和分析，主要体现在()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","将BIM模型作为与设计方沟通的平台，控制设计进度",true,{"key":16,"text":17,"correct":18},"B","对专项施工方案进行模拟",false,{"key":20,"text":21,"correct":18},"C","对施工图进行深化设计",{"key":23,"text":24,"correct":18},"D","对BIM实施全过程进行规划",{"key":26,"text":27,"correct":14},"E","进行设计错误的检测，在施工开始之前解决所有设计问题，确保设计的可实施性，减少返工","AE","B、C选项是属于施工阶段的BIM应用，D选项不属于基于BIM对建设项目的展示和分析。",{"id":6,"name":31,"category":32,"favorite":33},"BIM工程师","建筑工程",0]