[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-858473":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},858473,535,2,"多选题","风管安装的顺序通常为()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","先上层后下层",true,{"key":16,"text":17,"correct":18},"B","先支管后干管",false,{"key":20,"text":21,"correct":14},"C","先干管后支管",{"key":23,"text":24,"correct":18},"D","先水平管后主管",{"key":26,"text":27,"correct":14},"E","先主管后水平管","ACE","风管安装顺序：先上层后下层，先干管后支管，先主管后水平管。",{"id":6,"name":31,"category":32,"favorite":33},"BIM工程师","建筑工程",0]