[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-858444":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},858444,535,2,"多选题","下列属于工程变更的表现形式的是()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","更改工程有关部位的标高、位置和尺寸",true,{"key":16,"text":17,"correct":14},"B","增减合同中约定的工程量",{"key":19,"text":20,"correct":21},"C","变更施工单位",false,{"key":23,"text":24,"correct":21},"D","变更工程成本",{"key":26,"text":27,"correct":14},"E","改变有关工程的施工顺序和时间安排","ABE","工程变更的表现形式。",{"id":6,"name":31,"category":32,"favorite":33},"BIM工程师","建筑工程",0]