[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-858430":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},858430,535,2,"多选题","下列选项关于BIM技术在建造阶段中的应用说法正确的是()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","BIM技术在工程项目成本控制中的应用主要体现在快速精确的成本核算、预算工程量动态查询与统计、限额领料与进度款支付管理、以施工预算控制人力资源和物质资源的消耗、设计优化与变更成本管理等",true,{"key":16,"text":17,"correct":18},"B","BIM在施工节能中的主要应用内容有场地分析、土方量计算、施工用地管理及空间管理等",false,{"key":20,"text":21,"correct":14},"C","在施工阶段，基于共享BIM模型能够实现对设计变更的有效管理和动态控制",{"key":23,"text":24,"correct":14},"D","利用BIM技术可以对施工场地废弃物的排放、放置进行模拟，以达到减排的目的",{"key":26,"text":27,"correct":18},"E","基于BIM的物料管理包括且不限于安装材料BIM模型数据库、安装材料分类控制、用料交底及工程量自动计算等","ACD","BIM技术在建造阶段的应用。",{"id":6,"name":31,"category":32,"favorite":33},"BIM工程师","建筑工程",0]