[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-858417":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},858417,535,2,"多选题","目前在竣工阶段主要存在的问题有()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","验收人员仅仅从质量方面进行验收，对使用功能方面的验收关注不够",true,{"key":16,"text":17,"correct":14},"B","验收过程中对整体项目的把控力度不大",{"key":19,"text":20,"correct":21},"C","竣工阶段时间较短",false,{"key":23,"text":24,"correct":14},"D","竣工图纸难以反映现场的实际情况","ABD","",{"id":6,"name":28,"category":29,"favorite":30},"BIM工程师","建筑工程",0]