[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-858387":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},858387,535,2,"多选题","通过基于BIM的4D施工进度模拟，能够对施工过程进行有效进度管理，主要包括()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","基于BIM施工组织，对工程重点和难点的部位进行分析，制定切实可行的对策",true,{"key":16,"text":17,"correct":14},"B","依据BIM模型，确定施工方案，排定计划，划分流水段",{"key":19,"text":20,"correct":21},"C","基于BIM模型的信息协同平台，有效提升信息传输效率及管理进度",false,{"key":23,"text":24,"correct":14},"D","通过对BIM模型施工过程的模拟动画展示对现场施工进度进行每日管理",{"key":26,"text":27,"correct":21},"E","通过BIM模型的参数化特性，在工程变更时，有效减少模型调整工作量，有利于施工进度的保障","ABD","通过4D施工进度模拟，能够完成以下内容：基于BIM施工组织，对工程重点和难点的部位进行分析，制定切实可行的对策；依据模型，确定方案，排定计划，划分流水段；BIM施工进度编制用季度卡来编制计划；将周和月结合在一起，假设后期需要任何时间段的计划，只需在这个计划中过滤一下即可自动生成；做到对现场的施工进度进行每日管理。",{"id":6,"name":31,"category":32,"favorite":33},"BIM工程师","建筑工程",0]