[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-858381":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},858381,535,2,"多选题","下列属于BIM技术在进度管理中的主要应用措施有()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","BIM施工进度模拟",true,{"key":16,"text":17,"correct":18},"B","建立成本的5D(3D实体、时间、成本)关系数据库",false,{"key":20,"text":21,"correct":14},"C","BIM建筑施工优化系统",{"key":23,"text":24,"correct":18},"D","项目动态控制系统","AC","进度管理小标题。",{"id":6,"name":28,"category":29,"favorite":30},"BIM工程师","建筑工程",0]