[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-858363":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},858363,535,2,"多选题","工程建设项目的进度管理是指对工程项目各建设阶段的()制定计划，将该计划付诸实施。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","工作内容",true,{"key":16,"text":17,"correct":14},"B","工作程序",{"key":19,"text":20,"correct":14},"C","持续时间",{"key":22,"text":23,"correct":14},"D","逻辑关系",{"key":25,"text":26,"correct":27},"E","人员配詈",false,"ABCD","工程建设项目的进度管理是指对工程项目各建设阶段的工作内容、工作程序、持续时间和逻辑关系制定计划，将该计划付诸实施。",{"id":6,"name":31,"category":32,"favorite":33},"BIM工程师","建筑工程",0]