[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-858360":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},858360,535,2,"多选题","BIM在施工项目管理中的应用主要分为五各阶段的应用，下列属于其中的是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","初步设计阶段",false,{"key":16,"text":17,"correct":18},"B","深化设计阶段",true,{"key":20,"text":21,"correct":18},"C","建造准备阶段",{"key":23,"text":24,"correct":18},"D","建造阶段",{"key":26,"text":27,"correct":18},"E","竣工支付阶段","BCDE","BIM在施工项目管理中的应用主要分为五各阶段的应用，分别为招投标阶段、深化设计阶段、建造准备阶段、建造阶段和竣工支付阶段。",{"id":6,"name":31,"category":32,"favorite":33},"BIM工程师","建筑工程",0]