[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-858232":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},858232,535,2,"多选题","下列选项关于初步设计文件的深度要求说法正确的是()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","经过比选，确定设计方案",true,{"key":16,"text":17,"correct":14},"B","确定工程造价，据以控制工程投资",{"key":19,"text":20,"correct":14},"C","确定土地征用范围",{"key":22,"text":23,"correct":14},"D","据以编制施工图设计",{"key":25,"text":26,"correct":27},"E","据以进行施工",false,"ABCD","根据初步设计文件可进行施工准备，但不能直接进行施工。",{"id":6,"name":31,"category":32,"favorite":33},"BIM工程师","建筑工程",0]