[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-858214":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},858214,535,2,"多选题","项目BIM实施与应用指的是基于BIM技术对项目进行()管理的过程。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","信息化",true,{"key":16,"text":17,"correct":14},"B","集成化",{"key":19,"text":20,"correct":14},"C","协同化",{"key":22,"text":23,"correct":24},"D","自动化",false,{"key":26,"text":27,"correct":24},"E","单一性","ABC","项目BIM实施与应用并不是完全自动化的过程，且不是单一的功能及目标管理。",{"id":6,"name":31,"category":32,"favorite":33},"BIM工程师","建筑工程",0]