[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-858191":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},858191,535,2,"多选题","下列选项属于4D施工进度模拟内容的是()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","基于BIM模型，对工程重点和难点的部位进行分析，制定切实可行的对策",true,{"key":16,"text":17,"correct":14},"B","依据模型，确定方案，排定计划，划分流水段",{"key":19,"text":20,"correct":21},"C","附加力学性能，实现对施工方案的动态模拟",false,{"key":23,"text":24,"correct":14},"D","将周和月结合在一起，假设后期需要任何时间段的计划，只需在这个计划中过滤一下即可自动生成",{"key":26,"text":27,"correct":14},"E","做到对现场的施工进度进行每日管理","ABDE","4D模拟主要指的是基于BIM三维模型并附加时间信息对其施工进度进行模拟展示。",{"id":6,"name":31,"category":32,"favorite":33},"BIM工程师","建筑工程",0]