[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-858187":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},858187,535,2,"多选题","BIM为项目设计阶段专业协调提供的途径主要包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","协同设计",true,{"key":16,"text":17,"correct":18},"B","施工模拟",false,{"key":20,"text":21,"correct":14},"C","碰撞检查",{"key":23,"text":24,"correct":18},"D","性能分析",{"key":26,"text":27,"correct":18},"E","场地分析","AC","施工模拟是属于施工阶段的应用；场地分析、性能分析不属于专业间的协调应用。",{"id":6,"name":31,"category":32,"favorite":33},"BIM工程师","建筑工程",0]