[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-858183":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},858183,535,2,"多选题","将()结合起来，实现基于BIM的施工过程结构安全分析，能有效捕捉施工过程中可能存在的危险状态，指导安全维护措施的编制和执行，防止发生安全事故。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","BIM",true,{"key":16,"text":17,"correct":14},"B","4D技术",{"key":19,"text":20,"correct":21},"C","GIS",false,{"key":23,"text":24,"correct":21},"D","VR",{"key":26,"text":27,"correct":14},"E","时变结构分析方法","ABE","基于BIM的施工过程结构安全分析，结构力学分析涉及时变结构分析方法，施工过程的模拟涉及4D技术和BIM技术。",{"id":6,"name":31,"category":32,"favorite":33},"BIM工程师","建筑工程",0]