[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-858157":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},858157,535,1,"单选题","施工方案模拟优化指的是通过BIM可对项目重点及难点部分进行()模拟，按月、日、时进行施工安装方案的优化。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可见性",false,{"key":16,"text":17,"correct":18},"B","可建性",true,{"key":20,"text":21,"correct":14},"C","可视化",{"key":23,"text":24,"correct":14},"D","成本分析","施工方案模拟优化指的是通过BIM可对项目重点及难点部分进行可建性模拟，按月、日、时进行施工安装方案的分析优化，验证复杂建筑体系的可建造性，从而提高施工计划的可行性。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]