[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-858147":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},858147,535,1,"单选题","通过BIM可对项目重点及难点部分进行三维可建性模拟，按月、日、时进行施工安装方案的分析优化，验证复杂建筑体系(如施工模板、玻璃装配、锚固等)的可建造性，从而提高施工计划的可行性。以上描述没有体现BIM的()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","优化性",false,{"key":16,"text":17,"correct":14},"B","仿真性",{"key":19,"text":20,"correct":14},"C","可视化",{"key":22,"text":23,"correct":24},"D","一体化",true,"一体化指的是基于BIM技术可进行从设计到施工再到运营贯穿了工程项目的全生命周期的一体化管理。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]