[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-858124":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},858124,535,1,"单选题","下列选项关于土方开挖工程量的计算流程说法正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","首先依据地质勘察报告创建地下土层模型，接着建立土方开挖的BIM模型，将开挖模型与地质土层模型进行对比，最后生成土层开挖土方量清单表",true,{"key":16,"text":17,"correct":18},"B","首先生成土层开挖土方量清单表，接着建立土方开挖的BIM模型，将开挖模型与地质土层模型进行对比，最后依据地质勘察报告创建地下土层模型",false,{"key":20,"text":21,"correct":18},"C","首先开挖模型与地质土层模型进行对比，接着建立土方开挖的BIM模型，将依据地质勘察报告创建地下土层模型，最后生成土层开挖土方量清单表",{"key":23,"text":24,"correct":18},"D","首先依据地质勘察报告创建地下土层模型，接着建立土方开挖的BIM模型，生成土层开挖土方量清单表，最后将开挖模型与地质土层模型进行对比","",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]