[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-858105":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},858105,535,1,"单选题","下面哪一项不属于现阶段BIM在应用中的挑战()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","软件间数据交互难度大",false,{"key":16,"text":17,"correct":14},"B","目前市场上还没有成熟的适合中国国情的、应用与施工管理的BIM软件",{"key":19,"text":20,"correct":21},"C","无法进行成本控制",true,{"key":23,"text":24,"correct":14},"D","信息与模型关联难度大","现阶段BIM应用的挑战：①软件间数据交互难度大；②信息与模型关联难度大；③目前市场上还没有成熟的适合中国国情的、应用与施工管理的BIM软件；④对于大体量建筑，各专业模型集成后的数据较大，对软硬件要求高。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]