[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-858102":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},858102,535,1,"单选题","机电专业BIM施工工作计划中，首先需安排的工作是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","根据甲方的整体项目节点时间要求制定机电专业的施工计划节点",true,{"key":16,"text":17,"correct":18},"B","进行图纸深化设计",false,{"key":20,"text":21,"correct":18},"C","完成机电施工建模",{"key":23,"text":24,"correct":18},"D","完成机电施工设备材料的统计","",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]