[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-858047":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},858047,535,1,"单选题","BIM竣工模型形成后，土建和机电安装等各专业需要应用竣工模型指导施工，下列做法错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总承包单位应将竣工模型复制一份给各分包单位，以便于各分包单位在施工中运用",false,{"key":16,"text":17,"correct":18},"B","各专业可以打开别的专业的模型组",true,{"key":20,"text":21,"correct":14},"C","各专业应用时打开自己专业的模型组，根据专业系统逐一拆分模型(拆分亦即临时隐藏)",{"key":23,"text":24,"correct":14},"D","根据施工节点计划，控制模型的拆分段，应用完毕，应该及时关闭自己专业的模型组","",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]