[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-858036":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},858036,535,1,"单选题","BIM的4D是在3D建筑信息模型基础上，融人()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","成本造价信息",false,{"key":16,"text":17,"correct":14},"B","合同成本信息",{"key":19,"text":20,"correct":21},"C","进度控制信息",true,{"key":23,"text":24,"correct":14},"D","质量控制信息","BIM4D是在3D模型上加入了时间因素，融入了进度控制信息。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]