[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-858010":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},858010,535,1,"单选题","供货单位的项目管理工作主要在哪个阶段进行？( )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","运维阶段",false,{"key":16,"text":17,"correct":14},"B","设计阶段",{"key":19,"text":20,"correct":14},"C","规划阶段",{"key":22,"text":23,"correct":24},"D","施工阶段",true,"供货单位的项目管理工作主要在施工阶段进行，但它也涉及设计准备阶段、设计阶段、动用前准备阶段和保修期。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]