[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857999":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},857999,535,1,"单选题","()是为了保证完成项目的实际成本、费用不超过预算成本、费用的管理过程。它包括资源的配置，成本、费用的预算以及费用的控制等工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目成本管理",true,{"key":16,"text":17,"correct":18},"B","项目采购管理",false,{"key":20,"text":21,"correct":18},"C","项目工程量管理",{"key":23,"text":24,"correct":18},"D","项目质量管理","项目成本管理主要指的是对项目实施过程中的经费进行管理、控制、核算。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]