[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857997":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},857997,535,1,"单选题","BIM技术在进度管理中的优势说法不正确的是？()",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","碰撞检测，减少变更和返工进度损失",false,{"key":16,"text":17,"correct":18},"B","提高施工人员素质，加快进度",true,{"key":20,"text":21,"correct":14},"C","加快生产计划、采购计划编制",{"key":23,"text":24,"correct":14},"D","提升全过程协同效率","BIM技术在进度管理中的优势表。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]