[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857994":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},857994,535,1,"单选题","以下关于BIM技术在工程进度管理上的应用说法错误的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","通过BIM技术可以实现可视化的工程进度安排",false,{"key":16,"text":17,"correct":14},"B","通过BIM技术可以实现工程建设过程的模拟",{"key":19,"text":20,"correct":14},"C","通过BIM技术可以实现工程材料和设备供应过程的优化",{"key":22,"text":23,"correct":24},"D","通过BIM技术更容易实现施工成本控制",true,"D项属于BIM在施工成本管理上的应用。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]