[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857993":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},857993,535,1,"单选题","项目的实施、跟踪是一个控制过程，用于衡量项目是否向目标方向进展，监控偏离计划的偏差，在项目的()、时间和成本三大限制因素之间进行平衡，采取纠正措施使进度与计划相匹配。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","安全",false,{"key":16,"text":17,"correct":18},"B","范围",true,{"key":20,"text":21,"correct":14},"C","质量",{"key":23,"text":24,"correct":14},"D","进度","项目的实施、跟踪是一个控制过程，用于衡量项目是否向目标方向进展，监控偏离计划的偏差，在项目的范围、时间和成本三大限制因素之间进行平衡，采取纠正措施使进度与计划相匹配。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]