[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857977":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},857977,535,1,"单选题","以下关于BIM在深化设计中的应用说法错误的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","BIM模型可以协助完成机电安装部分的深化设计，包括综合布管图、综合布线图的深化",false,{"key":16,"text":17,"correct":14},"B","基于BIM模型对土建结构部分，包括土建结构与门窗等构件、预留洞口、预埋件位置及各复杂部位等施工图纸进行深化，可以减少工程施工阶段可能存在的错误",{"key":19,"text":20,"correct":14},"C","钢结构BIM三维建模出图进行深化设计的过程，本质上就是进行电脑预拼装、实现“所见即所得”的过程",{"key":22,"text":23,"correct":24},"D","玻璃幕墙深化设计就是对整个建筑的幕墙所有部位进行细化补充设计",true,"玻璃幕墙深化设计主要是对于整幢建筑的幕墙中的收口部位进行细化补充设计，优化设计和对局部不安全不合理的地方进行改正。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]