[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-857974":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},857974,535,1,"单选题","以下关于BIM在成本控制中的应用说法错误的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","BIM的出现，为限额领料提供了技术、数据支撑",false,{"key":16,"text":17,"correct":14},"B","通过BIM技术可以通过施工预算控制人力资源和物质资源的消耗",{"key":19,"text":20,"correct":14},"C","5D模型集三维建筑模型、施工组织方案、成本及造价等3部分于一体，能实现对成本费用的实时模拟和核算",{"key":22,"text":23,"correct":24},"D","通过BIM建立了具有资源和成本信息的预算信息模型后，需要通过人工计算建筑构件的资源用量及成本，用以指导实际材料物资的采购",true,"建立了具有资源和成本信息的预算信息模型后，采用BIM技术可以自动计算建筑构件的资源用量及成本，用以指导实际材料物资的采购。",{"id":6,"name":27,"category":28,"favorite":29},"BIM工程师","建筑工程",0]